ACHIEVEMENTS
Project wise achievements
Crisis Management Fund (CMF)
-
Project Start Date
2019-11-28
-
Project End Date
2020-11-28
-
AS Amount
1850.0 lakhs
-
Physical Progress
100.0 %
-
Sector
Disaster Risk Management
Vulnerability Reduction Fund VRF
-
Project Start Date
2019-11-28
-
Project End Date
2020-11-28
-
AS Amount
2600.0 lakhs
-
Physical Progress
100.0 %
-
Sector
Disaster Risk Management
COMMUNITY ENTERPRISE FUND (CEF) TO COMMUNITY DEVELOPMENT SOCIETY (CDS)
-
Project Start Date
2019-11-28
-
Project End Date
2021-05-30
-
AS Amount
3253.0 lakhs
-
Physical Progress
100.0 %
-
Sector
Livelihood
Reconstruction of 194.63 km of flood damagedcategory B (RoW 5mtrs) roads in seven districts viz. Ernakulam, Kottayam,Alappuzha, Pathanamthitta, Thrissur, Wayanad and Idukki
-
Project Start Date
2020-03-18
-
Project End Date
2021-12-31
-
AS Amount
6825.15 lakhs
-
Physical Progress
88.58 %
-
Sector
Roads & Bridges
Investigation and data collection of roads in 7 districts
-
Project Start Date
2020-02-28
-
Project End Date
2021-09-29
-
AS Amount
475.0 lakhs
-
Physical Progress
43.43 %
-
Sector
Roads & Bridges
Reconstruction of 5 flood damaged bridges of Local Self Government Department (LSGD) under Rebuild Kerala Initiative(RKI)
-
Project Start Date
2020-08-17
-
Project End Date
2021-12-31
-
AS Amount
1463.5 lakhs
-
Physical Progress
65.0 %
-
Sector
Roads & Bridges
ENTERPRISE RESOURCE PLANNING
-
Project Start Date
2020-10-27
-
Project End Date
2022-01-31
-
AS Amount
100.0 lakhs
-
Physical Progress
25.0 %
-
Sector
Livelihood
Establishing an integrated plastic waste management facility at KINFRA, Kuttipuram, Malappuram
-
Project Start Date
2020-08-28
-
Project End Date
2022-02-28
-
AS Amount
367.0 lakhs
-
Physical Progress
10.33 %
-
Sector
Sanitation
Land development and construction of compound wall around Clean Kerala Company Ltd. plant in KINFRA park at Kuttipuram.
-
Project Start Date
2019-12-06
-
Project End Date
2021-08-31
-
AS Amount
64.0 lakhs
-
Physical Progress
100.0 %
-
Sector
Sanitation
Reconstruction of Kurishupallippadi - Thadathilppadi - Kannadippara road in Parathodu town, Idukki district
-
Project Start Date
2021-08-18
-
Project End Date
2022-01-18
-
AS Amount
10.0 lakhs
-
Physical Progress
66.67 %
-
Sector
Roads & Bridges