ACHIEVEMENTS

Project wise achievements

Reconstruction of village offices (111 no.s) and other revenue buildings (36 no.s) under the Rebuild Kerala Initiative

  • Project Start Date

    2020-11-03

  • Project End Date

    2021-11-16

  • AS Amount

    13641.0 lakhs

  • Physical Progress

    87.82 %

  • Sector

    Disaster Risk Management

Reconstruction of Village offices (116 no's) & other Revenue Buildings (2 no's)

  • Project Start Date

    2021-02-12

  • Project End Date

    2022-03-31

  • AS Amount

    5381.0 lakhs

  • Physical Progress

    95.39 %

  • Sector

    Disaster Risk Management

Reconstruction of 28 Village offices under Rebuild Kerala Initiative

  • Project Start Date

    2021-02-25

  • Project End Date

    2022-03-31

  • AS Amount

    1260.1 lakhs

  • Physical Progress

    92.27 %

  • Sector

    Disaster Risk Management

Nammal Namukkayi

  • Project Start Date

    2019-12-28

  • Project End Date

    2021-11-30

  • AS Amount

    730.0 lakhs

  • Physical Progress

    100.0 %

  • Sector

    Disaster Risk Management

Digital Resurvey of 1550 villages in the State - Phase 1

  • Project Start Date

    2021-08-27

  • Project End Date

    2022-07-27

  • AS Amount

    45371.0 lakhs

  • Physical Progress

    52.46 %

  • Sector

    Land